Questions and Answers
in response to
Request For Proposals (RFP) for Architectural and Engineering Design Services – Fire Station 3.
From: Adam Solomonson, LEED AP
Question: Who will be on the selection committee?
Answer: The selection committee will be made up of Fire District Employees and members from the public experienced in evaluating proposals.
Question: On site, does the Fire Station (District?) know if any underground tanks for the church or fire station?
Answer: The Fire District is not aware of any underground tanks on the site and do not believe that any exist.
Question: Have you verified if the selection process will still include the evaluation of the design fee?
Answer: We posted Addendum #1 on our website this morning which removes the original request for a fee proposal in its entirety.
Question: Under Section 4 – Proposal Final Evaluation Score 35 points. Can you provide additional elaborations as to how the points will be weighted (i.e. Experience)?
Answer: Addendum #1 addresses Section 4 and reduces the point value to 25 points. We have also listed 5 things that will be used to evaluate the proposal documents.
From: Hans Ettlin, Kistler, Small White Team
Question: It is not readily apparent to me if KCFD is interested in actually obtaining LEED Certification or just designing to LEED standards and completing a score sheet tabulation. Can you clarify this for me? If pursing actual certification, should we include the LEED registration and certification fees in our proposal?
Answer: The submitted question was not received prior to the deadline for questions which was listed in the Schedule of Events on page 3 of the RFP as 2:00 PM on Friday December 16, 2011. Hence, we are not able to answer the question.
From: Leslie Hara Shick, Hara Shick Architecture, P.C.
Question: Can you please describe the Scope of Work required for the IT, Security and Access Control?
Question: If selected we would like to have 4 people at the interview, would this be permissible?
Question: On Page 4- General Terms and Conditions, Scope of Work, Items 11 and 12. is LEED certification required and/or what Level of LEED do you wish to pursue? See also pages 32 and 37 of the ARRA Guidelines.
Answer: The submitted questions were not received prior to the deadline for questions which was listed in the Schedule of Events on page 3 of the RFP as 2:00 PM on Friday December 16, 2011. Hence, we are not able to answer the question.
From: Bill, Nabil, Taha, Ph.D., P.E., Precision Structural Engineering Inc.
Question:
Since the time between the time we learned about this nice project and the submittal date is only about two weeks.And these two weeks include the weekend and a major holidays such as Christmas, I am asking if you could please extend the submittal day to preferably two more weeks to be on Friday January 13.
This is to:
- Give everyone a fair chance to prepare a decent response.
- Avoid giving unfair advantages to the two companies that already is familiar and worked on the projects before this RFP was announced.
- Give the county the opportunity to get better proposals and hopefully better service at lower design fee.
Answer: Due to the short timeframe to complete the construction of the Fire Station (December 12, 2012), we have chosen not to extend the deadline for submittal of proposals.